BANNING UNIFIED SCHOOL DISTRICT GENERAL OBLIGATION BOND MEASURE "R" ADOPTED BY THE CITIZENS OF BANNING, NOVEMBER 7, 2006. BALLOT WORDING:

 

Banning Unified Classrooms Construction, Safety and Repair Measure:
Shall Banning Unified School District construct, repair, upgrade and equip local schools including: upgrade electrical wiring, expand/add science labs and  libraries to meet current standards, address building safety issues, repair deteriorating restrooms/plumbing and HVAC;  construct additional classrooms and schools to accommodate enrollment and make necessary improvements to school facilities, by issuing $63,000,000 of bonds at interest rates within legal limits, requiring annual audits and continuing the citizens' oversight committee.

Of the $63,000,000 authorized by the voters on November 7, 2006, $37,500,000 of the bonds were sold and expended on Measure R projects. November 8, 2016, voters elected to reauthorize the selling of the remainder of the original amount, $25,500,000. The selling of these bonds will bring the District funds for Measure M projects.

Measure "R" projects:Go To Top of Page

  • Modernization of Hoffer Elementary  School - COMPLETE
  • Modernization of Hemmerling Elementary  School - COMPLETE
  • Modernization of Nicolet Middle School Science Building - COMPLETE
  • Construction of Banning High School Two-Story Classroom Addition - COMPLETE 
  • Construction began on Banning High School Athletic Complex January 2010. Complex opened late spring 2011 - PHASE I COMPLETE
  • Phase II Construction of Banning High School Athletic Complex began November 2013; Tennis Courts, Concession Stand, Restrooms & Parking. Dedication of the courts was August 2014 - PHASE II COMPLETE
  •  
     

    CITIZENS OVERSIGHT COMMITTEE MEMBERSGo To Top of Page

    The Citizens' Oversight Committee ("COC") consisted of seven (7) appointed members. Its principal purpose, the responsibility to inform the public concerning the expenditure of Measure R bond revenues by the Banning Unified School District ("District"). The last meeting for the oversight of Measure R bond revenues was held April 20, 2017, and the last Annual report was given June 29, 2017. This bond is now closed.